Supplier – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.
Supplier – Mechanic Lien
Mechanic lien must be prepared by an attorney. 120 days: Intent to lien has to be recorded within 120 days from last day of furnishing. 180 days: Lien must be filed within 180 days from last providing materials or labor.
Subcontractor – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.
Subcontractor – Mechanic Lien
Mechanic lien must be prepared by an attorney. 120 days: Intent to lien has to be recorded within 120 days from last day of furnishing. 180 days: Lien must be filed within 180 days from last providing materials or labor.
General Contractor – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.
General Contractor – Mechanic Lien
Mechanic lien must be prepared by an attorney. 180 days: Lien must be filed within 180 days from last providing materials or labor.
Timeframe to foreclose lien
Action to enforce must be commenced within 1 year from recording of lien.
Construction participants not covered by lien law
There are not any participants that are not covered.
Cost and damages not allowed in lien claim
Lien Law does not indicate any cost or damages not allowed