New York Lien Law

Supplier – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.

Supplier – Mechanic Lien
8 months: Generally, lien required within 8 months of last furnishing services. On single-family residential projects, within 4 months.

Subcontractor – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.

Subcontractor – Mechanic Lien
8 months: Generally, lien required within 8 months of last furnishing services. On single-family residential projects, within 4 months.

General Contractor – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.

General Contractor – Mechanic Lien
8 months: Generally, lien required within 8 months of last furnishing services. On single-family residential projects, within 4 months.

Timeframe to foreclose lien
Enforcement due 1 year from date of lien filing date.

Construction participants not covered by lien law
supplier to a supplier, unlicensed contractor

Cost and damages not allowed in lien claim
 A lienor may not include lost profits or delay damages in its lien claim.